Ressourcen temporär ersetzen/Temporarily replace resources

Recommended Posts

Hello,

first and foremost: Welcome to the Quest @Julia Mannagottera, and thanks for contributing!
Before I'll answer, let me quickly recap your question for users who don't speak German:

The Question is basically about how we can replace a resource on a project only for a certain amount of time, like 4 weeks, and not for the entire duration of the project?

In answering, I'd say that there is no one-click solution to this, unfortunately. My best practice would be to set this resource's allocation to zero for the 4 weeks (creating the necessary allocation segments, if need be). Then add the replacement to the project and allocate him only for those 4 weeks.

Would that be sufficient as a solution?

Does anybody else have something that works faster?

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


×
×
  • Create New...